PhoenixMart says construction goals are being met

Model buidout PhoenixMart
Model buidout PhoenixMart

By Kevin Reagan | Casa Grande Dispatch

PhoenixMart developers expect to have up to 275,000 square feet of concrete slab poured at the construction site by early next week.

Concrete trucks have been visiting the site, located at Florence Boulevard and Overfield Road, in recent days to pour at night. The company expects to have all 1.6 million square feet poured in the coming months.

Marshall Stahl, CEO of PhoenixMart, said the company is on schedule to meet construction goals set earlier this year for the huge sourcing center. He still expects the main shell of the PhoenixMart building to be up by the end of this year.

Continued:

Share this!

Additional Articles

News Categories

Get Our Twice Weekly Newsletter!

* indicates required

Rose Law Group pc values “outrageous client service.” We pride ourselves on hyper-responsiveness to our clients’ needs and an extraordinary record of success in achieving our clients’ goals. We know we get results and our list of outstanding clients speaks to the quality of our work.

October 2016
M T W T F S S
 12
3456789
10111213141516
17181920212223
24252627282930
31