Rosemont Mine opponents sue Army Corps over permit


This illustration of the planned Rosemont Mine shows where the copper ore will be processed and copper concentrate produced to be sent to a smelter.  / Courtesy of Hudbay and Rosemont Copper / Arizona Daily Star

By Tony Davis | Arizona Daily Star

Opponents of the Rosemont Mine filed suit Wednesday to overturn the U.S. Army Corps of Engineers’ recent approval of a permit for the $1.9 billion project.

The suit, filed in U.S. District Court, alleges that the Corps violated the Clean Water Act, the National Environmental Policy Act, the Administrative Procedures Act and several related rules and guidelines in approving the permit for the mine in the Santa Rita Mountains southeast of Tucson.

The Corps approved the permit on March 8. Its 81-page decision concluded that the project will serve the public interest, that its plan to mitigate for damages to washes on the mine site is adequate, and that some of the most damaging impacts that opponents say it will cause are not within the agency’s legal scope of analysis for the project.

READ ON:

Share this!

Additional Articles

Goodyear approves land purchase

By Mary Goldmeer | YourValley The Goodyear City Council unanimously approved a proposal to purchase a 13-acre parcel for $8.4 million. The acquisition, is planned to support future expansion

Read More »
News Categories

Get Our Twice Weekly Newsletter!

* indicates required

Rose Law Group pc values “outrageous client service.” We pride ourselves on hyper-responsiveness to our clients’ needs and an extraordinary record of success in achieving our clients’ goals. We know we get results and our list of outstanding clients speaks to the quality of our work.