City approves next phase of Litchfield Square development

By Your Valley

Litchfield Park City Council approved phase three of the long-awaited Litchfield Square development, which covers lighting, landscaping and roadway infrastructure, including construction of three new roundabouts.

Phase three, officially called GMP 3, is projected to cost no more than $7,284,278.

City plans show construction is set to begin Nov. 4 of this year and completed Oct. 8, 2022, a total of 238 days. Plans indicate construction on Litchfield Park road will begin next month, about Nov. 11.

READ ON:

Share this!

Additional Articles

News Categories

Get Our Twice Weekly Newsletter!

* indicates required

Rose Law Group pc values “outrageous client service.” We pride ourselves on hyper-responsiveness to our clients’ needs and an extraordinary record of success in achieving our clients’ goals. We know we get results and our list of outstanding clients speaks to the quality of our work.

October 2021
M T W T F S S
 123
45678910
11121314151617
18192021222324
25262728293031