Developers could soon pay for Mesa’s water infrastructure

By Cecilia Chan | East Valley Tribune

After developers squawked over a proposed one-time connection fee to Mesa’s water and wastewater systems, staff put two modifications on the table for council to consider that would help soothe their impact.

Council is expected Nov. 17 to introduce the Capacity Fee Ordinance, which would generate over the next decade $400 million to build the needed infrastructure to accommodate future growth. If adopted Dec. 1, the capacity fee takes effect Jan. 1.

“As we stand today, all of our systems are sized appropriately for our existing customer base,” said Chris Hassert, Water Resources director at the Nov. 6 study session. “So if we weren’t expanding anymore in the city, if we weren’t developing any vacant parcels, we would not have the need to build any new pipelines, expand plants – anything like that.”

The city is proposing that developers pay connection fees for water ranging from $7,719 to $1.4 million, depending on the meter size, which spans from 0.75 to 10 inches. For wastewater, the proposed range was $1,809 to $331,673.

READ MORE:

Share this!

Additional Articles

News Categories

Get Our Twice Weekly Newsletter!

* indicates required

Rose Law Group pc values “outrageous client service.” We pride ourselves on hyper-responsiveness to our clients’ needs and an extraordinary record of success in achieving our clients’ goals. We know we get results and our list of outstanding clients speaks to the quality of our work.

Casa Grande annexes 1,271 acres

By Justin Matthews | Pinal Post Key Points Casa Grande City Council unanimously approved annexing approximately 1,271 acres on December 1, 2025. The Project Saguaro annexation sits generally between Selma

Read More »