Scottsdale Civic Center costs escalate

(Photo via City of Scottsdale)

By Alex Gallagher | Scottsdale Progress

When the cost of the Civic Center was first estimated in 2018 and later approved in the 2019 bond election, planners inadvertently missed some expenses that, along with inflation, are now driving up the total cost of the re-do.

The initial $27.3 million budget did not account for the aging infrastructure beneath the Civic Center discovered only after construction began. Nor was the cost of lighting and audio/visual equipment factoredn into the project.

Inflation also has been a driving force in the escalation of the total Civic Center renovation cost as prices for construction materials were rising well before the project broke ground in late 2021.

READ ON:

Share this!

Additional Articles

Maricopa permitting roundup

(Disclosure: Rose Law Group represents D.R. Horton, Meritage, and Richmond American.) By Monica D. Spencer | InMaricopa.com Here is a list of permits issued between April 11

Read More »

Lennar Q2 results

(Disclosure: Rose Law Group represents Lennar.)  By Leah Draffen | Builder Lennar reported lower second quarter earnings as it maintained sales volume in a high‑rate, affordability‑constrained housing

Read More »
News Categories

Get Our Twice Weekly Newsletter!

* indicates required

Rose Law Group pc values “outrageous client service.” We pride ourselves on hyper-responsiveness to our clients’ needs and an extraordinary record of success in achieving our clients’ goals. We know we get results and our list of outstanding clients speaks to the quality of our work.