SR-24 Extension and Central Arizona Parkway project moves forward

(Disclosure: Rose Law Group represents a coalition of property and business owners throughout Pinal County who have worked to bring new transportation infrastructure to the region.)

By San Tan Valley

Pinal County’s SR-24 Extension and Central Arizona Parkway project is advancing to address the growing transportation needs of San Tan Valley and nearby communities. This major infrastructure project aims to create a new four-lane parkway that will extend State Route 24 east of Ironwood Road, connecting to the Central Arizona Project (CAP) canal, and continuing south to Ocotillo Road. The first phase of this project, with an estimated completion date in the coming years, is designed to alleviate traffic congestion, improve regional connectivity, and support ongoing population growth.

Key Project Milestones
The project is progressing with several important milestones:

  • November 20, 2024: ADOT will present an Intergovernmental Agreement (IGA) to the Pinal County Board of Supervisors, a crucial step in formalizing partnerships for the project.
  • November 29, 2024: Completion of the Draft Design Concept Report (DCR), which outlines the project’s alignment, environmental impact, and design considerations.
  • April 30, 2025: ADOT is set to complete its review and approval of the DCR, finalizing the design for construction.

READ ON:

Share this!

Additional Articles

News Categories

Get Our Twice Weekly Newsletter!

* indicates required

Rose Law Group pc values “outrageous client service.” We pride ourselves on hyper-responsiveness to our clients’ needs and an extraordinary record of success in achieving our clients’ goals. We know we get results and our list of outstanding clients speaks to the quality of our work.

November 2024
M T W T F S S
 123
45678910
11121314151617
18192021222324
252627282930